<current_state>
|
|
Phase 2 is COMPLETE. All plans executed, verified, and committed. Ready for Phase 3.
|
|
</current_state>
|
|
|
|
<completed_work>
|
|
|
|
- 02-01-PLAN.md: Provider infrastructure (7.7 min) — GpsDataManager ChangeNotifier, SettingsProvider, OverlayProvider
|
|
- 02-02-PLAN.md: MultiProvider wiring + screen migration (3.8 min) — main.dart rewrite, SpeedometerScreen migration
|
|
- Verification: 20/20 must-haves passed, VERIFICATION.md created
|
|
- Requirements: STATE-01 through STATE-07 marked Complete
|
|
|
|
</completed_work>
|
|
|
|
<next_action>
|
|
Plan Phase 3: Overlay Refactor — fix overlay data staleness and communication reliability
|
|
/gsd:plan-phase 3
|
|
</next_action>
|