phase, task, total_tasks, status, last_updated
phase task total_tasks status last_updated
02-provider-migration 5 5 complete 2026-02-10

<current_state> Phase 2 is COMPLETE. All plans executed, verified, and committed. Ready for Phase 3. </current_state>

<completed_work>

  • 02-01-PLAN.md: Provider infrastructure (7.7 min) — GpsDataManager ChangeNotifier, SettingsProvider, OverlayProvider
  • 02-02-PLAN.md: MultiProvider wiring + screen migration (3.8 min) — main.dart rewrite, SpeedometerScreen migration
  • Verification: 20/20 must-haves passed, VERIFICATION.md created
  • Requirements: STATE-01 through STATE-07 marked Complete

</completed_work>