Phase 1 fully executed and verified (9/9 must-haves). Ready to resume with Phase 2 (Provider Migration). Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
3.9 KiB
phase, task, total_tasks, status, last_updated
| phase | task | total_tasks | status | last_updated |
|---|---|---|---|---|
| 01-foundation | complete | 5 (3 in plan 01, 2 in plan 02) | phase_complete | 2026-02-09T22:15:00Z |
<current_state> Phase 1 (Foundation) is fully complete. Both plans executed, verified (9/9 must-haves passed), committed, and documented. The project is at the boundary between Phase 1 and Phase 2.
Branch: feature/gps-manager-architecture
Last commit: 8e3ad7f docs(01): complete foundation phase
</current_state>
<completed_work>
Plan 01-01: Infrastructure, Logger, Constants, Models (12.8 min)
- Task 1: Directory structure (screens/, widgets/, providers/, models/, config/), Logger utility, 3 constants files (GpsConfig, TimingConfig, OverlayConfig)
- Task 2: SpeedUnit and ColorThemes moved to config/, ProcessedGpsData/OverlayMessage/ThemeModel extracted to models/
- Task 3: All imports rewired, 106+ print/customDebugPrint calls replaced with Logger, old files deleted
- Commits:
2b2fc8f,5122be4,a0d93d7
Plan 01-02: Screen Extraction (6.8 min)
- Task 1: SpeedometerScreen (802 lines) extracted to screens/speedometer_screen.dart
- Task 2: OverlaySpeedometer (303 lines) extracted to screens/overlay_screen.dart, main.dart slimmed to 39 lines
- Non-blocking checkpoint: Physical device regression testing recommended (not yet performed)
- Commits:
bc36076,ad077d1
Phase completion:
- Verification: 9/9 must-haves passed (01-VERIFICATION.md)
- Requirements ORG-01 through ORG-08 marked Complete in REQUIREMENTS.md
- ROADMAP.md, STATE.md updated
- Commit:
8e3ad7f</completed_work>
<remaining_work>
Optional before Phase 2:
- Physical device regression test (non-blocking checkpoint from 01-02)
- Consider analysis_options.yaml to suppress SCREAMING_SNAKE lint warnings (21 info-level)
Phase 2: Provider Migration (not yet planned)
- Replace setState with Provider pattern for reactive state management
- Requirements: STATE-01 through STATE-07
- Depends on Phase 1 (satisfied)
- Expected: 2-3 plans
- HIGH RISK: Async lifecycle complexity needs pre-audit </remaining_work>
<decisions_made>
- SCREAMING_SNAKE naming for behavioral constants (GpsConfig, TimingConfig, OverlayConfig)
- Logger utility with 4 severity levels replaces all print()/customDebugPrint() globally
- OverlayMessage typed class for IPC instead of raw Maps (toMap/fromMap serialization)
- ThemeModel delegates palette storage to ColorThemes (separation of concerns)
- Layer-first directory structure (screens/, widgets/, providers/, models/, config/, services/)
- main.dart as pure entry point (39 lines — main(), overlayMain(), SpeedoApp only) </decisions_made>
The codebase is now ready for Phase 2's Provider migration. The key challenge will be threading Provider through the existing async patterns: GPS stream subscription, overlay lifecycle management, timer-based heartbeats, and widget lifecycle observers. SpeedometerScreen alone has 5+ async patterns that need careful handling during the migration.
Phase 3 (Overlay) and Phase 4 (GPS) both depend on Phase 2 but are independent of each other — they could potentially run in parallel after Phase 2 completes.
<next_action>
Resume with: /gsd:discuss-phase 2 or /gsd:plan-phase 2
The discuss step is recommended because Phase 2 has HIGH RISK async complexity. Gathering context first (auditing async patterns, deciding GpsDataManager disposal strategy) will produce better plans. </next_action>