Commit Graph

13 Commits

Author SHA1 Message Date
Mikkeli Matlock ee73a1a48d docs(02): phase 2 planned, paused before execution
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-10 11:31:42 +09:00
Mikkeli Matlock 755c4b7b06 fix(02): revise plans based on checker feedback
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-10 11:17:01 +09:00
Mikkeli Matlock 630cf1c578 docs(02): create phase plan
Phase 02: Provider Migration
- 2 plan(s) in 2 wave(s)
- Wave 1: Create providers (GpsDataManager + SettingsProvider + OverlayProvider)
- Wave 2: Wire MultiProvider and migrate SpeedometerScreen
- Ready for execution
2026-02-10 11:13:29 +09:00
Mikkeli Matlock 8ff74b36e1 docs(02): research phase domain
Phase 02: Provider Migration
- Standard stack identified (provider v6.1.5+1)
- Architecture patterns documented (ChangeNotifier, Consumer, Selector)
- Pitfalls catalogued (7 common errors with solutions)
- Migration strategy validated against context decisions

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-10 11:05:17 +09:00
Mikkeli Matlock 919b239c6e docs(02): capture phase context
Phase 02: Provider Migration
- Implementation decisions documented
- Phase boundary established
2026-02-10 10:58:15 +09:00
Mikkeli Matlock 5c9f3d225e wip: foundation complete, paused before phase 2
Phase 1 fully executed and verified (9/9 must-haves).
Ready to resume with Phase 2 (Provider Migration).

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 21:58:56 +09:00
Mikkeli Matlock 8e3ad7f00c docs(01): complete foundation phase
Phase 1: Foundation - 2 plans executed in 19.6 minutes
- 01-01: Infrastructure, Logger, Constants, Models (12.8 min)
- 01-02: Screen extraction (6.8 min)
- Verification: 9/9 must-haves passed
- Requirements ORG-01 through ORG-08 marked Complete

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 21:55:01 +09:00
Mikkeli Matlock c3865b318a docs(01-02): complete screen extraction plan
Tasks completed: 2/2
- SpeedometerScreen extracted to screens/speedometer_screen.dart (802 lines)
- OverlaySpeedometer extracted to screens/overlay_screen.dart (303 lines)
- main.dart slimmed to 39 lines (entry points only)

Phase 1 Foundation: COMPLETE (2/2 plans, 19.6 min total)

SUMMARY: .planning/phases/01-foundation/01-02-SUMMARY.md
2026-02-09 21:48:38 +09:00
Mikkeli Matlock 88293716a4 docs(01-01): complete plan execution with summary and state updates
- Create 01-01-SUMMARY.md: Comprehensive execution summary with 12.8 min duration
- Update STATE.md: Progress 50% (1/2 plans complete), velocity metrics, decisions table
- Document 5 key decisions made during execution
- Record zero deviations, one minor bug (missing import)
- Phase 1 ready to proceed with plan 01-02
2026-02-09 21:37:02 +09:00
Mikkeli Matlock 7e9ed22e40 fix(01): revise plans based on checker feedback
- Clarified ThemeModel delegation rationale (Issue 1)
- Documented why Task 3 is one atomic task (Issue 2)
- Made customDebugPrint deletion step unambiguous (Issue 3)

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 21:13:09 +09:00
Mikkeli Matlock 7f8075b76d docs(01): create phase plan
Phase 01: Foundation
- 2 plan(s) in 2 wave(s)
- 2 autonomous, 0 checkpoint-only
- Ready for execution

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 21:08:34 +09:00
Mikkeli Matlock c3b38c25a2 docs(01): research phase domain
Phase 01: Foundation
- Standard stack identified
- Architecture patterns documented
- Pitfalls catalogued

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 21:02:20 +09:00
Mikkeli Matlock d41e29a1b9 docs(01): capture phase context
Phase 01: Foundation
- Implementation decisions documented
- Phase boundary established

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 20:54:59 +09:00