Mikkeli Matlock
07d446d912
docs(03): research overlay communication and staleness patterns
...
Phase 3: Overlay Refactor
- Standard stack identified: flutter_overlay_window 0.5.0, retry package, permission_handler
- Architecture patterns documented: OverlayService wrapper, timestamp-based staleness, error surfacing
- Pitfalls catalogued: communication blackhole, permission race conditions, opacity performance
- User decisions integrated: 3s dim threshold, 10s dashes, no recovery animation, 30s grace period
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-11 18:54:38 +09:00
Mikkeli Matlock
9001a42196
docs(03): capture phase context
...
Phase 03: Overlay Refactor
- Implementation decisions documented
- Phase boundary established
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-10 23:14:45 +09:00
Mikkeli Matlock
a27e6b7f3e
docs(02): complete provider migration phase
...
- Phase 2 verified: 20/20 must-haves passed
- STATE-01 through STATE-07 marked Complete in REQUIREMENTS.md
- VERIFICATION.md confirms codebase matches all success criteria
- ROADMAP.md and STATE.md updated for phase completion
2026-02-10 22:28:42 +09:00
Mikkeli Matlock
09c80011b8
docs(02-02): complete MultiProvider wiring and screen migration plan
...
Tasks completed: 2/2
- Task 1: Wire MultiProvider in main.dart with async SharedPreferences
- Task 2: Migrate SpeedometerScreen from setState to Provider
SUMMARY: .planning/phases/02-provider-migration/02-02-SUMMARY.md
2026-02-10 22:21:04 +09:00
Mikkeli Matlock
3c5ce89ded
docs(02-01): complete provider infrastructure plan
...
Tasks completed: 3/3
- Task 1: Add provider dependencies and refactor GpsDataManager to ChangeNotifier
- Task 2: Create SettingsProvider for theme and unit state
- Task 3: Create OverlayProvider for overlay lifecycle and messaging
SUMMARY: .planning/phases/02-provider-migration/02-01-SUMMARY.md
2026-02-10 22:11:49 +09:00
Mikkeli Matlock
ee73a1a48d
docs(02): phase 2 planned, paused before execution
...
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-10 11:31:42 +09:00
Mikkeli Matlock
755c4b7b06
fix(02): revise plans based on checker feedback
...
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-10 11:17:01 +09:00
Mikkeli Matlock
630cf1c578
docs(02): create phase plan
...
Phase 02: Provider Migration
- 2 plan(s) in 2 wave(s)
- Wave 1: Create providers (GpsDataManager + SettingsProvider + OverlayProvider)
- Wave 2: Wire MultiProvider and migrate SpeedometerScreen
- Ready for execution
2026-02-10 11:13:29 +09:00
Mikkeli Matlock
8ff74b36e1
docs(02): research phase domain
...
Phase 02: Provider Migration
- Standard stack identified (provider v6.1.5+1)
- Architecture patterns documented (ChangeNotifier, Consumer, Selector)
- Pitfalls catalogued (7 common errors with solutions)
- Migration strategy validated against context decisions
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-10 11:05:17 +09:00
Mikkeli Matlock
919b239c6e
docs(02): capture phase context
...
Phase 02: Provider Migration
- Implementation decisions documented
- Phase boundary established
2026-02-10 10:58:15 +09:00
Mikkeli Matlock
5c9f3d225e
wip: foundation complete, paused before phase 2
...
Phase 1 fully executed and verified (9/9 must-haves).
Ready to resume with Phase 2 (Provider Migration).
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-09 21:58:56 +09:00
Mikkeli Matlock
8e3ad7f00c
docs(01): complete foundation phase
...
Phase 1: Foundation - 2 plans executed in 19.6 minutes
- 01-01: Infrastructure, Logger, Constants, Models (12.8 min)
- 01-02: Screen extraction (6.8 min)
- Verification: 9/9 must-haves passed
- Requirements ORG-01 through ORG-08 marked Complete
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-09 21:55:01 +09:00
Mikkeli Matlock
c3865b318a
docs(01-02): complete screen extraction plan
...
Tasks completed: 2/2
- SpeedometerScreen extracted to screens/speedometer_screen.dart (802 lines)
- OverlaySpeedometer extracted to screens/overlay_screen.dart (303 lines)
- main.dart slimmed to 39 lines (entry points only)
Phase 1 Foundation: COMPLETE (2/2 plans, 19.6 min total)
SUMMARY: .planning/phases/01-foundation/01-02-SUMMARY.md
2026-02-09 21:48:38 +09:00
Mikkeli Matlock
88293716a4
docs(01-01): complete plan execution with summary and state updates
...
- Create 01-01-SUMMARY.md: Comprehensive execution summary with 12.8 min duration
- Update STATE.md: Progress 50% (1/2 plans complete), velocity metrics, decisions table
- Document 5 key decisions made during execution
- Record zero deviations, one minor bug (missing import)
- Phase 1 ready to proceed with plan 01-02
2026-02-09 21:37:02 +09:00
Mikkeli Matlock
7e9ed22e40
fix(01): revise plans based on checker feedback
...
- Clarified ThemeModel delegation rationale (Issue 1)
- Documented why Task 3 is one atomic task (Issue 2)
- Made customDebugPrint deletion step unambiguous (Issue 3)
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-09 21:13:09 +09:00
Mikkeli Matlock
7f8075b76d
docs(01): create phase plan
...
Phase 01: Foundation
- 2 plan(s) in 2 wave(s)
- 2 autonomous, 0 checkpoint-only
- Ready for execution
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-09 21:08:34 +09:00
Mikkeli Matlock
c3b38c25a2
docs(01): research phase domain
...
Phase 01: Foundation
- Standard stack identified
- Architecture patterns documented
- Pitfalls catalogued
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-09 21:02:20 +09:00
Mikkeli Matlock
d41e29a1b9
docs(01): capture phase context
...
Phase 01: Foundation
- Implementation decisions documented
- Phase boundary established
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com >
2026-02-09 20:54:59 +09:00